Tender sum for construction contracts
The tender sum is the overall pricing figure proposed by a tendering contractor in accordance with the tender pricing document.
The objective of the tender pricing document is to:
- Enable like-for-like comparison between tenders and the cost plan (pre-tender estimate).
- Enable the cost consultant to assess where value lies within the different tenders (such as foundations or finishes) allowing assessment of value for money.
- Identify any significant differences in pricing between tenderers to ensure the design has been correctly interpreted.
- Identify areas of savings that might be negotiated with tenderers while still in competition.
- Form the financial basis of the tender report.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.
Building Regulations and Building Safety Act
CIOB publishes free advice for non-domestic clients.
Building Safety Newsletter from MHCLG.
An extraordinary record of steel engineering worldwide.
Households living near new pylons to save on bills.
ECA warns growth must not outpace grid capacity or skills.
The role of the client and decision making
CIOB response to built environment professions call for evidence.
Construction's sustainability reporting revolution
Tracking upfront embodied carbon with digital tools.
ECA welcomes procurement reforms
Public spending must back British jobs and skills.